PMP Case Study Questions with Answers and Explanations

  • 2026-11-19
PMP case study questions cover showing a bike-share station and cartons on a packaging conveyor.

Two bike-share stations are up and running 99% of the time. At one station, nearly a third of new riders come back within 30 days. At the other, fewer than one in five do. If the sponsor asks what to change, which piece of evidence would you use first?

These six original PMP case study questions give you two projects to work through. The first asks you to diagnose an adoption problem and design a test. The second asks you to handle a confirmed issue while an unrelated risk is still open. Each case has an exhibit, three questions, and an explanation for every answer choice.

PMI’s July 2026 PMP Exam Content Outline describes case questions that use a detailed scenario. A case may include supporting diagrams or graphics. The practice below uses short tables so you can work through the evidence before making each decision.

How to Work Through a PMP Case Study

  1. Find the goal. Look for the result the sponsor or customer cares about. A well-performing system can still fall short of its adoption target.
  2. Mark the timing. Separate what has already happened from what is still uncertain. A forecast can also trigger action if the governance plan says so.
  3. Check who can act. Look for what the team can change, what it needs to escalate, and who can approve a change to a commitment.

Start with either case. Use its exhibit for all three questions and apply any new fact in a question to that question only. Choose an answer before opening the explanation.

Case A. Bike-Share Pilot Adoption

A city is piloting bike-share stations at two commuter hubs. The sponsor tracks the share of first-time riders who take another trip within 30 days. The pilot team can adjust signs and rider onboarding within its budget. Permanent station moves require separate approval.

Exhibit A. Pilot metrics and rider observations
Measure or observation Pilot evidence
Repeat rides within 30 days Target 30%. East Hub 33%, West Hub 18%.
West Hub user feedback In 12 of 16 observed attempts, riders had trouble finding the rack from the bus exit.
Station uptime Target 98%. East Hub 99%, West Hub 99%.
West Hub access The station is next to an accessible route. Any signage trial must keep that route clear.

Question 1. Investigating low adoption

Which action should the project manager take first to address low repeat use at West Hub?

  • A. Ask the sponsor to approve a permanent station move.
  • B. Run a short walk-through with riders and station staff to test the wayfinding problem.
  • C. Spend the remaining pilot budget on a citywide campaign.
  • D. Ask the maintenance team to improve station uptime.
See the answer and explanation for question 1

Correct answer B. The local observations point to a plausible barrier that the team can test within its authority.

  • A. A permanent move requires approval. Proposing one now would jump to a costly response before the team checks what is keeping riders away.
  • B. A walk-through can validate where riders lost the route and identify a small adjustment the team can test.
  • C. A citywide campaign spends money before the team understands why riders at one hub struggle.
  • D. Both hubs already exceed the uptime target, so maintenance addresses a weaker explanation.

Question 2. Designing an adoption experiment

A walk-through confirms that riders miss a turn after leaving the bus exit. Which pilot change would best test whether clearer wayfinding helps?

  • A. Move both stations to locations with higher foot traffic.
  • B. Change signage, prices, and onboarding at both hubs at the same time.
  • C. Set the West Hub repeat-use target to 18% for the pilot.
  • D. Place temporary signs clear of the access route and track West Hub repeat rides for a comparable 30-day cohort.
See the answer and explanation for question 2

Correct answer D. The team has confirmed a plausible cause and can test a reversible change against the outcome it wants to improve.

  • A. Moving both stations requires separate approval and would test new locations instead of the effect of clearer signs.
  • B. Changing several factors together makes it difficult to assess the effect of signs.
  • C. Changing the threshold leaves the wayfinding barrier in place and gives the team no evidence about a fix.
  • D. A focused signage trial preserves access. A comparable 30-day cohort gives the team evidence on the intended outcome.

Question 3. Reporting evidence and outcomes

The sponsor asks how the team will decide whether the signage trial supports a wider rollout. What should the project manager propose?

  • A. Compare repeat use for similar rider cohorts, review feedback and access observations, and document the remaining uncertainty.
  • B. Count the signs installed and declare success when every sign is in place.
  • C. Use East Hub uptime as the only measure of West Hub success.
  • D. Approve rollout when a single rider says the signs are helpful.
See the answer and explanation for question 3

Correct answer A. The sponsor needs evidence of adoption alongside evidence that the trial still preserves access.

  • A. Comparable cohorts, rider feedback, and access observations support an informed decision and expose gaps in the evidence.
  • B. Installation is an output. It provides no direct evidence that the change improved adoption.
  • C. Uptime describes a different measure and this option takes it from the other hub.
  • D. One comment can explain a possible mechanism. The rollout decision needs broader evidence.

The adoption metric tells you where to investigate. The observations tell you what to test. When you report the result, keep those roles separate and compare riders who had the same amount of time to return. For additional examples of evaluating a solution against business needs, see the PMI-PBA guide on solution evaluation.

Case B. Packaging Line Pilot

A manufacturer is piloting a new carton format on a single packaging line. The project manager maintains a risk and issue log and follows an approved governance plan. The steering group decides whether to extend the pilot or change its scope.

Exhibit B. Risk status, issue status, and escalation threshold
Item Project record
R1. Label supply A strike could delay the next batch. A second supplier is on standby.
R2. Case sealing The sealing head failed this morning and the line stopped for four hours. The agreed temporary workaround is available.
Schedule escalation Notify the steering group when forecast delay exceeds two working days.
Forecast after workaround The team forecasts a three-working-day delay.

Question 4. When a risk becomes an issue

Which action should the project manager take for R2 after the equipment failure is confirmed?

  • A. Raise R1's probability rating and leave R2 under observation.
  • B. Close R2 and wait for the monthly risk review before assigning follow-up.
  • C. Record the failure as an issue, link it to R2, and assign an owner to coordinate the workaround and follow-up.
  • D. Open a request to extend the pilot and treat the failure as resolved once the request is logged.
See the answer and explanation for question 4

Correct answer C. The line stoppage has occurred and requires active ownership.

  • A. R1 concerns a different uncertainty. Updating it leaves the current line stoppage without follow-up.
  • B. Waiting for the regular review delays a response to a problem that already happened.
  • C. An issue record, an owner, and a linked risk entry preserve context and make the response trackable.
  • D. A potential extension is a separate governance decision. Logging a request does not resolve the failure.

Question 5. Applying an escalation threshold

The forecast has been verified at three working days. What should the project manager do next under the governance plan?

  • A. Notify the steering group with the forecast, impact, and available recovery options.
  • B. Wait until two working days of actual delay have passed.
  • C. Move the approved end date by three working days and inform the steering group afterward.
  • D. Notify only the equipment technician because the workaround is available.
See the answer and explanation for question 5

Correct answer A. The plan triggers escalation on the forecast. Three working days exceed the two-day threshold.

  • A. The steering group needs the verified forecast and recovery options now so it can make any decisions within its authority.
  • B. The trigger is based on forecast delay, so waiting for actual delay misses the stated threshold.
  • C. The project manager would be changing the approved date before the responsible group makes its decision.
  • D. Equipment staff can support recovery. The steering group still needs notification under the plan.

Question 6. Separating open risks from current issues

There is still no confirmed strike. What should the project manager do with R1 while the team handles the sealing issue?

  • A. Convert R1 into a current issue because R2 has occurred.
  • B. Activate the standby supplier immediately without checking the agreed trigger or commercial impact.
  • C. Remove R1 from the risk register until the sealing head is repaired.
  • D. Keep R1 open, verify the standby supplier's readiness, and confirm who monitors the trigger.
See the answer and explanation for question 6

Correct answer D. The strike remains uncertain and the planned response depends on its own trigger.

  • A. A separate equipment failure does not establish that the supplier strike has occurred.
  • B. Activating the standby supplier may incur cost or contractual commitments before the trigger warrants it.
  • C. Removing the risk creates a monitoring gap while the threat remains credible.
  • D. Maintaining ownership and checking response readiness keeps the contingency usable if the trigger occurs.

Several actions can happen in parallel. The issue owner can coordinate the workaround, the project manager can notify the steering group about the forecast, and the supplier risk owner can keep monitoring the strike. For more context on decision rights and reporting, see the PMI-PMOCP guide to project governance.

Review the Decision You Missed

For each missed question, write down the exhibit fact or rule that changes the answer. If you picked an early escalation in Case A, review who could authorize each action and what evidence the team had at that point. If you waited in Case B, reread what the governance plan says about the forecast. Explaining the deciding fact is a good way to check whether you can apply the same judgment in a different project.

Add case practice to your study schedule with the PMP certification exam guide and study plan.

Reference

Leave A Reply

Your email address will not be published. Required fields are marked *

You May Also Like

  • Oct 7, 2026
PMI Certified Professional in Managing AI (PMI-CPMAI) is a certification for people who need to manage artificial intelligence projects without...
  • Oct 6, 2026
Scheduling looks simple until a real project starts moving. A Gantt chart can look perfectly clean on Monday and become...
  • Oct 5, 2026
A network can be technically perfect and still solve the wrong problem. A migration can finish on schedule and still...
  • Oct 4, 2026
If you work in networking or infrastructure, you have probably seen a technically sound project fail for reasons that had...