PMP Project Management Professional® — Question 8
PMI PMP Part 1 · question 8 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 8
For the third day in a row during a daily standup, a team member discusses problem-solving for a critical stage in the project. As a result, the standup meeting runs over time. Though the conversation is useful, some team members’ body language has indicated that they are frustrated. What should the project manager do to resolve this situation?

Discussion
Loading comments…