Question 78


A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan that the team member believes will be cheaper and equally effective.
What should the project manager do?