Question 191


A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for their operational use. There is no delay in the schedule. However, the customer is still not happy about the outcome as some of the systems that were handed over are no longer useful because the environment changed.
What should the project manager have done to avoid this?