Question 184
For the third day in a row during a daily standup, a team member discusses problem-solving for a critical stage in the project. As a result, the standup meeting runs over time. Though the conversation is useful, some team members’ body language has indicated that they are frustrated.
What should the project manager do to resolve this situation?