PMP Project Management Professional® — Question 153
PMI PMP Part 8 · question 153 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 153
During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress.
How should the project manager revise the report and demonstrate the project is on schedule?