PMP Project Management Professional® — Question 144
PMI PMP Part 8 · question 144 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 144
A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs)for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly.
What should the project manager do to help with the estimate development?