PMP Project Management Professional® — Question 135
PMI PMP Part 7 · question 135 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 135
Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?