PMP Project Management Professional® — Question 133
PMI PMP Part 7 · question 133 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 133
A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client.
What should the project manager do first?