PMP Project Management Professional® — Question 120
PMI PMP Part 6 · question 120 of 200 in the PMP Project Management Professional® question bank. Pick an answer to check it, or join the discussion below.
Question 120
A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests.
Which two actions should the project manager take until the approval is received? (Choose 2)
Checking access…