Question 113
A project manager is working on a large event and developing budgets for sign off. The stakeholders and project sponsor are all working remotely, using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox.
How should the project manager proceed?