Question 84
Based on its board’s mandate, an organization drafts a new business strategy to meet future challenges, put the business on track, and meet growth expectations. Key to this are upgrading the IT infrastructure and strategic direction to transition the computing platform from onsite to cloud-based, thereby optimizing costs, and providing scalability, performance and high availability.
How should the program manager use the program mission statement to engage program stakeholders?