Program Management Professional (PgMP)® — Question 73
PMI PGMP Part 4 · question 73 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 73
A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?