Program Management Professional (PgMP)® — Question 71
PMI PGMP Part 4 · question 71 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 71
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?