Program Management Professional (PgMP)® — Question 44
PMI PGMP Part 3 · question 44 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 44
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed. What should program A’s program manager update and review first with the stakeholders?