Question 190
A hotel chain initiates program to expand meeting offering to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program. As a result, the program manager must do which of the following?