Question 166
A widespread occurrence of influenza strikes a metropolitan area, affecting two of the five project teams included in the program. The program manager realizes that this scenario was never considered and several of the program management plans do not include adequate provisions for this type of situation. What techniques should be used to manage stakeholder expectations during this crisis?