Program Management Professional (PgMP)® — Question 158
PMI PGMP Part 8 · question 158 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 158
You are managing program which is composed of 4 projects: A, B, C, D. A steering committee meeting is planned for this coming Friday. And the board wants to see your program’s EVM parameters. The table below reflects the EVM data by your project managers:

What can you conclude for your program?