Program Management Professional (PgMP)® — Question 145
PMI PGMP Part 8 · question 145 of 200 in the Program Management Professional (PgMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 145
You are managing a program which is entering the closure phase. In order to properly close the program, you read the closure criteria which have been documented, and you compare them with your situation. From the list below, what is NOT a closure criterion for the program?
Checking access…