Question 119
You will have a meeting with the GB, and in this meeting you will discuss ongoing and completed risks response. You have to minimize the risks impact, and you have assigned core team members who are responsible for the overall risk management. You have hold the first review meeting for your program, and it will followed by a meeting with your GB, which direct you to response on risks.
When you have prepared the risk response, what is the next step?