PMI Scheduling Professional (PMI-SP)® — Question 88
PMI SP Part 5 · question 88 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 88 (Q90)
You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your reject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?