PMI Scheduling Professional (PMI-SP)® — Question 79
PMI SP Part 5 · question 79 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 79 (Q81)
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?
Checking access…

Discussion
Loading comments…