PMI Scheduling Professional (PMI-SP)® — Question 61
PMI SP Part 4 · question 61 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 61 (Q63)
You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment.
Management has asked you to begin reporting and forecasting your project’s health based on a moving average, extrapolation, trend estimation, and growth curve. What type of forecasting method is management asking you to use?