PMI Scheduling Professional (PMI-SP)® — Question 38
Pmi Sp Part2 2 · question 38 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 38 (Q19)
You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

Based on this figure, what is the critical path of this project?