PMI Scheduling Professional (PMI-SP)® — Question 36
Pmi Sp Part2 2 · question 36 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 36 (Q17)
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?