Question 30 (Q11)


Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI) for this project?

Checking access…

Discussion

Loading comments…

← Back to question bank