PMI Scheduling Professional (PMI-SP)® — Question 26
Pmi Sp Part2 2 · question 26 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 26 (Q7)
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?