PMI Scheduling Professional (PMI-SP)® — Question 168
PMI SP Part 9 · question 168 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 168 (Q170)
You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project’s budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
Checking access…