Question 164 (Q166)


Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: MeasurementsValues BCWP (or EV) 425 BCWS (or PV) 400 ACWP (or AC) 510 What is the schedule performance index (SPI) of the project at the current point of time?