PMI Scheduling Professional (PMI-SP)® — Question 147
Pmi Sp Part8 2 · question 147 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 147 (Q129)
You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.
How much float can you use on Activity G if Activity B actually takes eight days to complete?