PMI Scheduling Professional (PMI-SP)® — Question 130
PMI SP Part 8 · question 130 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 130 (Q152)
You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?