PMI Scheduling Professional (PMI-SP)® — Question 11
PMI SP Part 2 · question 11 of 197 in the PMI Scheduling Professional (PMI-SP)® question bank. Pick an answer to check it, or join the discussion below.
Question 11 (Q32)
Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

Discussion
Loading comments…