Question 94 (Q96)


A multiyear infrastructure megaproject is underway, with various contractor teams reporting a wide array of potential risks. The risk manager has identified major risks, including changes in regulatory policies, technological shifts, volatile material prices, and particularly unpredictable weather conditions that could significantly delay project delivery. What three actions should the risk manager take? (Choose 3)