During the planning phase of an engineering project, the project team performs a qualitative risk analysis. The aim is to evaluate and rank risks to determine which ones require immediate attention and resources. This helps the team concentrate on threats that could significantly impact the project’s success. What is the primary purpose of conducting a qualitative risk analysis during the planning phase?