Question 75 (Q77)
A construction project is underway. Schedules and cost estimates are gathered to perform a quantitative risk analysis. The goal is to assess the combined effects of time and cost uncertainties. The risk manager aims to determine a contingency budget using low, medium, and high ranges from the analysis results. Which technique should the risk manager use to identify a 70%, 80%, and 90% confidence level range in selecting the appropriate contingency budget?