Question 72 (Q74)


A software development project in a financial organization is approaching its midway review. The project has multiple stakeholders, including executive leadership, team members, government, and key customers, each with varying levels of expertise and interest in risk-related details. The project sponsor has asked the risk manager to prepare a risk status report for this midway review. What should the risk manager do?