Question 69 (Q71)


A food processing company is launching project that will deliver a new processing plant. During project planning, the company’s legal team provides an overview of items needed for regulatory compliance. Several stakeholders have expressed that maintaining the project schedule is most important and that the regulatory compliance items should be prioritized in a way that will not impact the schedule. What should the risk manager do first to ensure each risk is considered based on the overall project impact?