Question 64 (Q66)


During a project review, the risk manager identifies a previously mitigated risk has experienced a change in its impact due to evolving regulatory standards. Initially, the residual risk was assessed with a probability of 10% and an impact of US$400,000. New regulations have increased the impact to US$650,000 and the probability to 20%. What is the revised expected monetary impact of the residual risk?