PMI Risk Management Professional (PMI-RMP)® — Question 58
PMI RMP Part 3 · question 58 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 58 (Q59)
A team is leading a product development project in a volatile market. The risk manager identifies challenges such as supplier delays and fluctuating customer demands. The sponsor asks for a plan to proactively monitor these challenges, but the project manager is concerned about how to address constant changes in the environment. Which criteria should the risk manager propose for developing an effective risk management plan for the project?