Question 47 (Q48)


The risk manager identifies a critical risk related to potential delays in obtaining environmental permits. This risk is assessed with a probability of occurrence at 40% and an impact of US$500,000. After evaluating risk responses, the team decides to implement a mitigation strategy that lowers the probability of occurrence to 25% and the impact to US$300,000.
What is the expected monetary impact of the residual risk after implementing the mitigation strategy?