Question 45 (Q46)


A risk manager has recently been assigned to a large cross-functional project that is already underway. In reviewing existing project artifacts, the risk manager discovers that risk planning documents are incomplete and lacking key information. Several risks have been realized and the project manager is requesting response guidance from the risk manager.
What should the risk manager do?