PMI Risk Management Professional (PMI-RMP)® — Question 36
PMI RMP Part 2 · question 36 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 36
A project team is preparing a project plan for a government-funded project with multiple stakeholders, including government employees. The project sponsor requests the risk manager estimates the potential costs associated with delays that may arise from government employees, due to bureaucratic processes and other administrative factors. How should the risk manager approach this task?