PMI Risk Management Professional (PMI-RMP)® — Question 23
PMI RMP Part 2 · question 23 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 23
The customer’s executive team requests the project sponsor accommodate the financial impact of a force majeure event that occurred during the project execution. The sponsor asks the risk manager to assess the risk to determine if it falls within the organizational limits. What should the risk manager do?