Question 195 (Q198)
A large infrastructure project to construct a high-speed railway line is underway. The risk manager notes that the project’s success depends on several conditions and is constrained by specific limitations identified during the initiation phase. During the planning phase, the risk manager identifies potential risks arising from these conditions and limitations. What should the risk manager do to address the identified risks?