PMI Risk Management Professional (PMI-RMP)® — Question 189
PMI RMP Part 10 · question 189 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 189 (Q192)
A risk manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the timeline, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is actually three months behind schedule. The organization’s risk appetite is low.
What should the risk manager do?