PMI Risk Management Professional (PMI-RMP)® — Question 18
PMI RMP Part 1 · question 18 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 18
A risk manager had to mitigate delay risks in the delivery of a component in a manufacturing project by procuring from an alternate vendor with shorter lead times. This has led to another risk, because the project team may need additional training on how to install this specific component. What should the risk manager do?