PMI Risk Management Professional (PMI-RMP)® — Question 16
PMI RMP Part 1 · question 16 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 16
The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks: however, some of the risk response strategies created secondary risks. What should the risk management team have done to manage this situation?