PMI Risk Management Professional (PMI-RMP)® — Question 157
PMI RMP Part 8 · question 157 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 157 (Q160)
A project manager is overseeing a software development project. The project has multiple dependencies, including third-party vendors and a shifting regulatory landscape. The team has identified a few risks informally, but no structured risk identification exercises have taken place yet. A risk manager is brought on to mitigate the tight schedule and potential external impacts after the project manager realizes that formalizing the risk management process is crucial for the project’s success.
Which measure should the risk manager implement?