PMI Risk Management Professional (PMI-RMP)® — Question 141
PMI RMP Part 8 · question 141 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 141 (Q143)
During the final phase of a software implementation project several documented risks have either been mitigated successfully or resulted in minimal impact. As the project nears completion, there is a need to ensure all project documents are up to date. What should the risk manager do?