PMI Risk Management Professional (PMI-RMP)® — Question 138
PMI RMP Part 7 · question 138 of 197 in the PMI Risk Management Professional (PMI-RMP)® question bank. Pick an answer to check it, or join the discussion below.
Question 138 (Q140)
In a critical system upgrade project, a key supplier notifies the team of a potential delay in delivering an essential component. This delay could severely impact the project timeline and budget The risk manager has convened a meeting with the project team and relevant stakeholders to figure out possible risk responses to deal with this risk. Which action should the risk manager prioritize?